2021 Bond Measure
In November 2021, Mesa County Voters approved a Bond Measure to rebuild Grand junction High School. Just as the district shared detailed information during the course of numerous projects that were funded by the 2017 Bond Measure, we remain committed to posting updated information throughout the Grand Junction High School construction process.
As the new Grand Junction High School is being constructed, we're reminded that this building is not just a school; it's a place for investing in the future, making memories, and community collaboration. Thank you, Grand Junction, for saying "YES!" to GJHS.
Construction Timeline
- June 1, 2022 - Groundbreaking
- May 2024 - Construction of new building complete
- Summer 2024 - Move furniture into new building, receive certificate of occupancy, demolish old school
- August 2024 - Students and staff will start the 2024-25 school year in the NEW building
- Aug.-Dec. 2024 - Renovation of the East Gym and final site development
- End of 2024 (anticipated) - Projected complete