Rocky Mountain Elementary Bond Work
Before bond-funded Priority Improvement Projects began, Rocky Mountain Elementary was in acceptable condition with some notable facility needs. The most significant included aging HVAC rooftop units and controls, parking lot resurfacing, technology updates, and limited interior finish improvements. Educationally, the school meets or exceeds most needs for teaching and learning, but did require additional special education instructional space.
Bond-funded improvements at Rocky Mountain Elementary include safety system upgrades and targeted enhancements to learning spaces and campus areas that better support students and staff.
Completed Work Includes:
-
Added fire alarm
-
Added fencing & landscaping improvements
-
Media center & SPED room improvements
-
Modular improvements
-
Added bollards
Remaining Work Includes:
-
Permanent doors and hardware
-
Site furnishings
-
Shade structure
-
Gym pads
-
Marker boards